- March 2024
- Sept 2024
- March 2025
- Sept 2025
- Feb 2026
- Mar 24
- Sep 24
- Mar 25
- Sep 25
- Feb 26

Current Completion : 92%
Status as of 5th January 2026 : Internal plastering and External plastering completed (100%)
Vitrified flooring and Toilets Tiling Completed (100%)
Putty work completed (100%)
Elevation cladding completed (95%)
Basement plastering completed (100%)
Windows fixing completed (100%)
Grills fixing completed (100%)
Door fixing completed (100%)
Staircase railings fabrication InProgress (100%)
Granite work completed (100%)
External texture and Dampproof completed (100%)
Basement flooring concrete and Ramp completed (100%)
Compound wall blockwork InProgress (50%)
Terrace waterproofing and concrete completed (100%)
Lift installation InProgress (50%)
Project Status : Ahead of Schedule
Next Update on 5th Feb 2026