- March 2024
- Sept 2024
- March 2025
- Sept 2025
- April 2026
- Mar 24
- Sep 24
- Mar 25
- Sep 25
- Apr 26

Current Completion : 93%
Status as of 28th Feb 2026 : Internal plastering and External plastering completed (100%)
Vitrified flooring and Toilets Tiling Completed (100%)
Putty work completed (100%)
Elevation cladding completed (100%)
Basement plastering abs painting completed (100%)
Windows fixing completed (100%)
Grills fixing completed (100%)
Door fixing completed (100%)
Staircase railings fabrication completed (100%)
Granite work completed (100%)
External texture and Dampproof completed (100%)
Basement flooring concrete and Ramp completed (100%)
Compound wall blockwork and plastering completed (Left side and front)(60%)
Terrace waterproofing and concrete completed (100%)
Lift installation completed(100%)
Elevation Jalli work InProgress (100%)
Internal Final painting work InProgress(40%)
External painting InProgress (70%)
Project Status : Nearing Completion
Next Update on 31th Mar 2026